Project Code : PRJ/TCC/2423
MSE Wall designing and installation and Installation of Chemical Anchors with 60Kn pull out power (Sub Contract)
Designed and installed the manufactured (customized) eyebolts with special chemical on the natural rock with 6000Kg pulling power in order to build an MSE (Mechanically Stabilized Earth wall) WALL SYSTEM in the Lusail underpass.
Project : Upgrade of Lusail Circuit – Racetrack and Infrastructure.
Client : Ashghal
Consultant :
Contractor : GET
Our client : Chairman Trading & Contracting
Project Starts in Jan, 4th – 2024
Project Status : Running.
Project Code : PRJ/TCC/2321
Restaurant Interior Fit-out works including FF,FS,FA, Electrical,HVAC and MEP works (Main Contractor)
Project : Fit-out works for Meal Miracle Restaurant in Doha Souq Mall (Shop No:3 / M floor / Al Nasser)
Client : Restaurant Meal Miracle
Consultant : Al Keshaf Consultants
Sub – Contractors performed for Fire Fighting, Fire Alarm, Fire Safety, Electrical works, HVAC works, Kitchen Hood and ducts works. TeamEx worked for Plumbing and Civil fit-outs.
Project started in December 2022
Project Status : Running.
Project Code : PRJ/TCC/2320
Excavation of trenches & manholes (Sub Contract)
Project : Construction of remaining works, Road & Infrastructure in Al Mearad and Southwest Muither PCKG1 (DW044-P01).
Client : Ashghal
Consultant : Ital Consult
Contractor : QBS Construction
Project yet to start
Project Status : Awarded.
Project Code : PRJ/TCC/2319
Excavation of trenches & manholes (Sub Contract)
Project : Construction of remaining works, Infrastructure FS gaps for Bani Hajer and Al Rayyan Stadium PCKG2 (DN117-P02).
Client : Ashghal
Consultant : Ital Consult
Contractor : QBS Construction
Project Starts in May, 17th – 2023
Project Status : Running.
Project Code : PRJ/TCC/2318
Excavation of trenches & manholes (Sub Contract)
Project : C-316 (Roads & Infra in AL EBB & LEABAIB-PKG 2) project.
Client : Ashghal
Consultant : KEO International
Contractor : Qatar Building Company (QBC)
Project Starts in April, 26th – 2023
Project Status : Running.
Project Code : PRJ/TCC/2117
Excavation of trenches (Sub Contract)
Project : Ras Abroug Project
Client : Qatar Airways
Consultant :
Contractor : Construction Development Company (CDC)
Project Starts in December, 29th – 2021
Project Status : Completed.
Project Code : PRJ/TCC/2116
Enabling Works for Dialysis & Diabetes Centre for Hamad Medical Corporation @ Al-Wabb (Sub Contract)
Project : Enabling Works for Dialysis & Diabetes Centre for HMC
Client : Hamad Medical Corporation
Consultant :
Contractor : UCE
Project Starts in October, 17th – 2021
Project Status : Completed.
Project Code : PRJ/TCC/2115
Excavation of Trenches and Manholes @ Ain Khalid (Sub Contract)
Project : Flood Prevention Scheme Project (FPS-PHASE 3)
Client : Ashghal
Consultant : Parsons
Contractor : HBK
Project Starts in September, 1st – 2021
Project Status : Completed.
Project Code : PRJ/TCC/2114
Excavation of Trenches and Manholes @ Al Wakra -West (Sub Contract)
Project : Roads & Infrastructure in Wakra West (PH 2, PKG 14)- Package 2
Client : Ashghal
Consultant : Dorsch Qatar
Contractor : UCE
Project Starts in June, 29th 2021
Project Status : Running
Project Code : PRJ/TCC/2112
Excavation of Trenches and Chambers @ Al Kharatiyat/Izghawa (Sub Contract)
Project : DN002 P02 Road & Infrastructure in Al Kharatiyat and Izghawa Phase 01/ Package 02
Client : Ashghal
Consultant :
Contractor : UCC-INFRA JV (Royal China)
Project Starts in May, 4th 2021
Project Status : Completed
Project Code : PRJ1/TCS/2011
Excavation of Trenches and Chambers & Bulk Excavation @ Al Wukair (Sub Contract)
Project : GWC Logistics Park – Phase I
Client : GWC
Consultant : QDC
Contractor :Redco International W.L.L
Project Starts in July, 15th 2020
Project Status 01 : Running 2nd phase (started from 18th of October 2021)
Project Status 02 : Completed.
Project Code : PRJ1/TCS/2010
Construction of Compound Wall & Fabrication & Installation of Gate for a Private Farm House @ Zekreet/Dukhan (Main Contract)
Project : Compound Wall & Gate for Farm House
Client : Private Land Lord
Consultant : N/A
Contractor : TEAMEX
Project Starts in January, 20th 2020
Project Status : Completed
Project Code : PRJ1/TCS/1909
Fabrication & Installation of Heavy Trucks Barricade Gates (Gate for Maximum Height) @ Barwa Village
Project : Fabrication & Installation
Client :Barwa Properties Holding Co.
Consultant : —-
Contractor :Waseef
starts on 05th of December 2019
Project Status : Completed
Project Code : PRJ1/TCS/1908
Excavation, Backfilling & Compaction @ US Army Base (Sub Contract)
Project : Falcon 3 / Phase II
Client :US Army Base
Consultant : —-
Contractor :United Construction Est.
starts on 28th of August 2019
Project Status : Completed
Project Code : PRJ1/TCS/1805
Excavation,Interlock Installation & Asphalt Repair Works @ Barwa Village (Sub Contract)
Project : Excavation & Road Repair Works
Client :Barwa Properties Holding Co.
Consultant : Waseef
Contractor :Waseef
starts on 05th of January 2019
Project Status : Completed
Project Code : PRJ1/TCS/1806
300,000 square meter area demolition & clearance including asphalt and concrete roads, Office cabins, Slabs, Steel and debris at green line track yard at Umm Al Afai. (Sub Contract)
Client : Qatar Rail
Consultant :N/A
Contractor :PORR
Project Starts in December, 12th 2018
Project Status : Completed
Project Code : PRJ1/TCS/1807
Excavation of Trenches and Chambers, Material Haulage & Equipment Rental @ Al Saliya (Sub Contract)
Project : Pipelines & Roads Project for Al Saliya Army Camp
Client : Ashghal
Consultant : Parsons Brinckerhoff
Contractor :Qatar Building Company (QBC)
Project Starts in December, 2nd 2018
Project Status : Completed
Project Code : PRJ1/TCS/1804
Excavation of Trenches and Chambers, Material Haulage & Equipment Rental @ Umm Salal (Sub Contract)
Project : Umm Salal Workers’ Accomodation & Roads Project
Client : Ashghal
Consultant : ITAL CONSULT
Contractor :United Construction Establishment (UCE)
Project Starts in November, 2018
Project Status : Completed
Project Code : PRJ1/TCS/1803
Material Haulage & Equipment Rental @ Al Wajba (Rental of Heavy Equipments & Trucks)
Project : Al Bustan Roads Project
Client : Ashghal
Consultant :
Contractor :Hyundai E & C
Project Starts in August, 2018
Project Status : Completed
Project Code : PRJ1/TCS/1802
Excavation of Trenches and Chambers @ Lusail
Project : Redline Qatar Rail Project
Client : Qatar Rail
Consultant :
Contractor : RLR JV ( Worked through DOREX Engineering)
Project Status : Completed
Project Code : PRJ1/TCS/1801
Limestone Supply & Equipment Rental @ Wakrah
Project : Redline Qatar Rail Project
Client : Qatar Rail
Consultant :
Contractor :Fujita Corporation
Project Status : Completed
Project Code : PRJ1/TCS/1701
Excavation of Trenches and Chambers, Material Haulage & Equipment Rental @ Lusail/Alkhor
Project : Alkhor Highway Project
Client : Ashghal
Consultant :KEO International
Contractor : TEKFEN Construction | Sub Contractor : DOREX Engineering
Project Status : Completed